In an opinion filed December 18, 2018, and later ordered published on January 10, 2019, the First District Court of Appeal affirmed a judgment denying appellant citizen groups’ writ petition challenging the City of St. Helena’s approval of an 8-unit, multifamily housing project and related demolition and design review. McCorkle Eastside Neighborhood Group, et al. v. City of St. Helena, et al. (2019) 31 Cal.App.5th 80. The decision applied the basic principle that CEQA does not apply to ministerial project approvals, and further clarified that CEQA does not apply to “mixed” discretionary/ministerial approvals where the “discretionary component” does not give the agency the authority to mitigate environmental impacts. It held that because the City’s discretion under its local design review ordinance does not extend to addressing environmental effects it does not implicate CEQA, and therefore the City’s reliance on the CEQA Guidelines’ Class 32 exemption was unnecessary.
Continue Reading Delineating CEQA’s Scope: First District Holds CEQA Does Not Apply To Ministerial Approval Of Multifamily Housing Project Allowed By Right Under Zoning Where City’s Discretion Was Limited To Design Review
CEQA Guidelines
CEQA Regulatory Update: OPR Provides Further Guidance on VMT, Asks for Input on GHGs; Guidelines Revisions Now Effective
Late last month the Governor’s Office of Planning and Research (OPR) released two documents of interest to CEQA practitioners. One is a discussion draft of a “CEQA and Climate Change Advisory.” The other is an update to its previous “Technical Advisory on Evaluating Transportation Impacts in CEQA.”
Continue Reading CEQA Regulatory Update: OPR Provides Further Guidance on VMT, Asks for Input on GHGs; Guidelines Revisions Now Effective
2018 Year-End CEQA Round-Up
As we draw near the close of another year, a number of recent CEQA developments bear noting.
Continue Reading 2018 Year-End CEQA Round-Up
Third District Holds Plumas County General Plan Update EIR Complies With CEQA And Update’s Compatible Use Determinations Do Not Violate Timberland Act
In an opinion filed October 19, and later ordered published on November 15, 2018, the Third District Court of Appeal affirmed a judgment upholding Plumas County’s First comprehensive update of its 1984 general plan, and rejecting arguments that the update violated the California Timberland Productivity Act of 1982 (the “Timberland Act” or “Act”) and that the related EIR violated CEQA. High Sierra Rural Alliance v. County of Plumas (2018) 29 Cal.App.5th 102.
Continue Reading Third District Holds Plumas County General Plan Update EIR Complies With CEQA And Update’s Compatible Use Determinations Do Not Violate Timberland Act
Fourth District Holds Addendum Process Authorized By CEQA, No New Findings Required
The Fourth District Court of Appeal (Div. 1) held in a published opinion filed October 24, 2018, that CEQA Guidelines § 15164 validly establishes an addendum process that is consistent with the CEQA statute, implementing and filling gaps in Public Resources Code § 21166. The Court also held that new findings under Public Resources Code § 21081 addressing a project’s significant impacts are not required when a lead agency approves an addendum to an EIR. Save Our Heritage Organisation v. City of San Diego (The Plaza de Panama Committee, Real Party in Interest) (2018) 28 Cal.App.5th 656.
Continue Reading Fourth District Holds Addendum Process Authorized By CEQA, No New Findings Required
Fourth District Holds San Diego County’s Threshold of Significance for Evaluating GHG Impacts Violates CEQA And Prior Writ
In a published opinion filed in consolidated appeals on September 28, 2018, the Fourth District Court of Appeal (Div. 1) affirmed the trial court’s judgment invalidating San Diego County’s adoption of a 2016 Guidance Document that established a generally applicable threshold of significance for GHG analysis of 4.9 metric tons of CO2e per service population per year. Golden Door Properties, LLC v. County of San Diego/Sierra Club, LLC v. County of San Diego (2018) 27 Cal.App.5th 892. The Court held the case was ripe because the 2016 Guidance Document’s GHG “Efficiency Metric” set forth the threshold of significance as generally applicable to project proposals; it held the document violated CEQA because it was not formally adopted by ordinance, rule, resolution or regulation through a public review process, and was not supported by substantial evidence adequately explaining how its service population number derived from statewide data constituted an appropriate GHG metric to use for all projects in unincorporated San Diego County. (CEQA Guidelines, §§ 15064.7(b), (c); Center for Biological Diversity v. California Department of Fish and Wildlife (2015) 62 Cal.4th 204, 227 (“CBD”).) The Court also held County’s adoption of the threshold of significance in advance of its required Climate Action Plan (CAP) constituted improper “piecemealing [of] environmental regulations” in violation of the Court’s earlier decision and the trial court’s second supplemental writ in the same litigation, which treated the CAP and thresholds of significance based on it as a single CEQA project and required completion of the CAP prior to the adoption of the thresholds of significance.
Continue Reading Fourth District Holds San Diego County’s Threshold of Significance for Evaluating GHG Impacts Violates CEQA And Prior Writ
Arguing Impacts By Proxy: Fourth District Holds CEQA Does Not Require EIR Absent Evidence That Subdivision Approval Actually Violated Applicable Land Use Regulations Adopted to Mitigate Environmental Impacts
In an opinion filed August 10, and later ordered published on September 7, 2018, the Fourth District Court of Appeal (Div. 2) affirmed a judgment denying Friends of Riverside’s Hills’ (FRH) writ petition challenging a residential development permit and related Negative Declaration issued by the City of Riverside (City) for a six-home, 11-acre subdivision in an environmentally sensitive area. Friends of Riverside’s Hills v. City of Riverside (Carlton R. Lofgren, as Trustee, etc., et al., Real Parties in Interest) (2018) 26 Cal.App.5th 1137.
Continue Reading Arguing Impacts By Proxy: Fourth District Holds CEQA Does Not Require EIR Absent Evidence That Subdivision Approval Actually Violated Applicable Land Use Regulations Adopted to Mitigate Environmental Impacts
Second District Holds CEQA Does Not Apply to San Luis Obispo County’s Issuance of Well Construction Permits Under Its Ministerial Governing Ordinance
In an opinion filed June 28, and later ordered published on July 27, 2018, the Second District Court of Appeal (Div. 6) affirmed the trial court’s judgment dismissing on demurrer a writ petition seeking to compel the County of San Luis Obispo to comply with CEQA in issuing well construction permits to four agricultural enterprises, mostly for vineyard irrigation. The Court held County’s governing local ordinance, which addresses only water quality issues and incorporates fixed technical standards for well construction from relevant Department of Water Resources (DWR) Bulletins, established a ministerial scheme for issuing such permits and does not confer “discretion to shape a well permit to mitigate environmental damage arising from groundwater overuse.” California Water Impact Network v. County of San Luis Obispo (Justin Vineyards and Winery, LLC et al., Real Parties in Interest) (2018) 25 Cal.App.5th 666.
Continue Reading Second District Holds CEQA Does Not Apply to San Luis Obispo County’s Issuance of Well Construction Permits Under Its Ministerial Governing Ordinance
Natural Resources Agency Announces Proposed CEQA Guidelines Modifications, Calls For Written Comments By July 20, 2018
Yesterday marked another significant step toward completion of the years-long journey of the first major CEQA Guidelines update in decades. The California Natural Resources Agency gave notice on July 2, 2018 of its modifications to OPR’s originally-proposed Guidelines changes. The Agency called for written comments, limited to these “15-day language” modifications, to be submitted by July 20, 2018. It noted that its staff will review and respond to comments received by that date as part of the formal rulemaking process, which began with the Agency (after receipt of OPR’s proposed Guidelines revisions) when it published its Notice of Proposed Rulemaking back on January 26, 2018.
Continue Reading Natural Resources Agency Announces Proposed CEQA Guidelines Modifications, Calls For Written Comments By July 20, 2018
Second District Holds CEQA’s Existing Facilities Categorical Exemption Applies To State Lands Commission/PG&E Lease Extension For Operation Of California’s Last Active Nuclear Power Plant Until 2025 Closure
In a published opinion filed June 13, 2018, the Second District Court of Appeal (Div. 4) affirmed a judgment denying a writ of mandate and declaratory relief in an action challenging the California State Lands Commission’s (“Commission”) determination that CEQA Guidelines § 15301’s categorical exemption for “existing facilities” applied to its renewal of PG&E’s leases of state-owned lands needed to operate the Diablo Canyon nuclear power plant until federal licensures expire in 2025. World Business Academy v. California State Lands Commission (Pacific Gas & Electric Company, Real Party in Interest) (2018) 24 Cal.App.5th 476. The Court rejected petitioner/appellant World Business Academy’s arguments that the consolidated lease replacement, which maintains the status quo at the plant until 2025, did not fall within the exemption, or was subject to the “unusual circumstances” exception, and also rejected arguments that it violated the public trust doctrine.
Continue Reading Second District Holds CEQA’s Existing Facilities Categorical Exemption Applies To State Lands Commission/PG&E Lease Extension For Operation Of California’s Last Active Nuclear Power Plant Until 2025 Closure